Alloy Phase One Settles into Steady Pace Toward Completion

After the rapid progress on stacking modular units, construction has settled into a steady pace toward completion.  All units are stacked and structural connections are completed.  Private balconies are under construction, exterior metal skin is underway on Building 2, and steel stairways and access balconies will commence in the next 2 weeks.  Inside the buildings, workers are busy connecting mechanical, plumbing and electrical systems to tie the modules together.  

 

The pool and deck will be poured in the coming weeks.  Additionally, construction of Alloy’s second phase has begun, offering 20 residential and live/work units. See recent aerial photos below.